News

The Louisiana Public Service Commission approved plans on Wednesday by the state utility company Entergy to build three new ...
The Richland Parish data center project, first announced in 2024, is one of the largest private capital investments in ...
This approval facilitates enhancements to the state’s electric grid, benefiting customers and preparing for future energy ...
Estimates suggest that the AI center will need roughly three times the amount of electricity that the city of New Orleans uses in a year ...
Meta’s $10 billion Louisiana data center has received regulatory approval from the Louisiana Public Service Commission.
When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
Louisiana utility regulators on Wednesday approved Entergy Louisiana’s plan to build new natural gas plants and transmission lines to power a $10 billion Meta data center in Richland Parish. The ...
Regulators clear Entergy's multibillion-dollar plan to build three major power stations to serve Meta's massive proposed data center.
Louisiana utility regulators approved a plan Wednesday, August 20, 2025 to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for ...
The Louisiana Public Service Commission (LPSC) has given the go-ahead for the installation of three natural gas turbines set to power Meta’s planned 2GW data center in Richland Parish, Louisiana.
Entergy's Louisiana unit received approval from the Louisiana Public Service Commission to move forward with infrastructure investments tied to Meta's new data center in Richland Parish, the utility ...